Progress Report (Punch List)

Friday, January 25, 2008

Progress Report (Punch Out)

We were out on site today and were able to complete:

  • Final Sanding and Painting of Stress cracks
  • Repaired O.S.B. "Punch Through" at bottom of Basement Stairs
The majority of the remaining punch items have been completed. There are some that are still in process as noted below.
We look forward to the completion of all items.


Previously completed items
  • Vent Pipes sealed
  • Adjusted doors
  • Adjusted strike plate on hall bathroom door
  • Pressure treated lumber installed garage
Remaining items
  • Clean out leaves upon good weather as discussed
  • Install Trim piece over kitchen cabinet
  • Replace warping cabinet doors in kitchen (on order 6 weeks)
  • Hot water tank control valve (on order 3 weeks remain)
  • Ceiling Fan Family Room
  • Install joint tape on some Hvac runs and insulate a return pipe in upstairs bonus area.